This assessment shows how an engineering team can find, rate and control the risks in a medium voltage power system and its substation. Eight hazards were chosen because they are plausible in design, operation and maintenance work. Arc flash during switching is the most severe, with an inherent score at the top of the Critical band, because the energy released can injure people and destroy equipment in a moment. Protection miscoordination, ageing transformers and switchgear, specification mismatch, supplier delays for spares, maintenance deviations, oil and gas leaks, and control data errors fill the rest of the register. Each risk is scored before controls and again after existing and added controls. Most risks fall to Medium or Low once added controls are in place, but arc flash remains High because its consequences stay severe. The first actions are a verified isolation procedure, a protection settings review, a critical spares agreement and a dated check of the as built drawings. The scores illustrate method only.
Scope
This assessment covers the design, commissioning, operation and maintenance of an electrical distribution system for a small industrial site, including a medium voltage incoming supply, a substation with switchgear and transformers, protection relays, low voltage distribution and the control systems that monitor them. It does not cover generation, grid transmission or any real installation. Voltage level, jurisdiction, plant age and supplier arrangements are assumptions made for teaching.
Context
The site has a grid connection at medium voltage, a main substation with two incoming feeders and a bus section, two power transformers, metal enclosed switchgear, protection relays with settings files, a standby generator and a supervisory control system. An in-house electrical engineering team designs changes and manages specifications, while a contractor carries out routine testing and maintenance under a permit to work system. Equipment comes from several suppliers with varying lead times. Each hazard is scored before controls to show its natural level, then again after existing controls and the additional controls that should be added.
Objectives, assets and stakeholders
The objective is to supply power safely and reliably, protect people and equipment, meet the legal duties that apply to the network, and keep the plant available for the process it serves. The assets in scope are the incoming supply, switchgear, transformers, cables, protection relays and their settings, the control and monitoring system, standby generation and the records that describe the plant. Stakeholders include operations and maintenance staff, contractors, the engineering design team, the site manager, production users, the network operator, insurers and regulators. Each risk has one owner role, and the engineering manager keeps the register current and reports to site leadership each quarter.