Power Generation and Energy Systems: Industry Report

Capacity additions, equipment lead times, supplier concentration and workforce constraints in the latest available data

  • Global for generation capacity and additions; United States for grid equipment lead times, gas turbine lead times, utility-scale solar cost and workfo...
  • Data period: Latest available data
  • 10 min read
  • 14 sources
  • Updated Oct 2026
  • Global renewable capacity additions 800GW per year Observed Global, Latest available data [1]
  • Renewable share of installed global power capacity 49percent Observed Global, End of latest available data [4]
  • Utility-scale battery all-in capex 125USD per kWh Observed Global excluding China and United States, Latest available data [11]
  • Gas power equipment backlog and slot reservations 116GW Observed Global, Most recent quarter [6]

Summary

Power generation and energy systems are expanding quickly, but the equipment needed to build, connect and firm that capacity is in short supply. Global renewable additions reached a record 800 GW in the latest available data, with solar supplying 75 percent 12. Battery storage was the fastest growing technology, with additions of about 110 GW 1. Supply chain strains and grid connection delays slowed growth in parts of the market 2. In the United States, average lead times for generator step-up transformers reached 144 weeks, and gas turbine backlogs now stretch for years 567. The principal risks are equipment shortages, rising gas turbine prices, heavy import dependence for large transformers and an aging, thinning electrical workforce 8913. Data gaps are significant: no verified figures exist for manufacturing yield, defect rates, safety incidents or emissions intensity. The outlook is for sustained demand for grid and firm generation equipment, so manufacturing capacity and workforce pipelines will largely set delivery performance. This assessment is the writer's interpretation of the sources.

Key findings

  1. 1

    Renewables set a record in the latest period

    Global renewable capacity additions reached a record 800 GW, with solar contributing 75 percent. Additions rose 16 percent despite supply chain strains and grid connection delays.

    Confidence: High
  2. 2

    US grid equipment lead times are measured in months to years

    Average US lead times are 144 weeks for generator step-up transformers, 128 weeks for power transformers and 44 weeks for medium-voltage switchgear. The figures come from secondary industry analysis, so definitions may vary.

    Confidence: Medium
  3. 3

    Gas turbine backlogs are large and primary disclosures confirm long queues

    GE Vernova's gas power backlog and slot reservations grew from 100 GW to 116 GW in the most recent quarter. Siemens Energy's gas services backlog reached 69 GW, with lead times of three years or more.

    Confidence: High
  4. 4

    Gas turbine prices rose sharply over a short window

    EPRI research reports that average gas turbine prices rose from roughly $2,000/kW to $3,000/kW in six months, nearly 50 percent. This is commentary on EPRI research, not a published price index.

    Confidence: Medium
  5. 5

    Large transformer supply depends heavily on imports

    Domestic production met only 20 percent of US large power transformer demand and about 50 percent of distribution transformer demand in the latest period.

    Confidence: Medium
  6. 6

    Skilled electrical labor is a binding constraint on delivery

    The Bureau of Labor Statistics counts about 821,000 working electricians and projects about 72,700 openings a year. Almost 30 percent of union electricians are between 50 and 70 years old. The projection is a forecast.

    Confidence: Medium

1Industry definition and scope

This report covers the equipment, projects and services that generate, store, convert, connect and maintain electricity. In the source pack, that scope includes solar photovoltaic (PV) and wind generation, battery storage, gas turbines, nuclear construction starts, and grid equipment such as power transformers, generator step-up transformers and medium-voltage switchgear 127.

The geographic scope is global for capacity and additions and United States for lead times, equipment costs and workforce data. The reporting period is the latest available data in each source. Sources cover different windows, so figures are not always comparable across sections.

Terminology is not uniform. Capacity is expressed in gigawatts (GW) of installed capacity. Battery costs are all-in capital expenditure (capex) in dollars per kWh 11. Lead times are reported as weeks from order to delivery, but the sources do not define the start and end points 7. Company backlogs are reported in GW or US dollars and may include slot reservation agreements 6.

Raw materials, manufacturing yield and end-of-life management fall within the brief's value chain, but the pack contains no verified figures for them. Those points are treated as data gaps.

2Market size, structure and value chain

Renewables accounted for 49 percent of installed global power capacity at the end of the latest period and 85.6 percent of power added 4. The International Energy Agency projects almost 4,600 GW of cumulative global renewable additions over a multi-year window, about double the prior pace. This is a forecast 3. The pack does not give a total market value in US dollars for the sector, so market size in money terms cannot be stated.

Within renewable additions, solar PV accounted for more than three-quarters and wind about 20 percent 2. Ember reports all-in capex for large utility-scale battery projects outside China and the US of about $125/kWh, with annual operating costs of around 2 percent of capex 11. Lawrence Berkeley National Laboratory reports a capacity-weighted installed cost of about $1.61/W AC for utility-scale solar projects in the US, up 1 percent. The figure is preliminary 10.

The value chain runs from raw materials through design and engineering, manufacture of turbines, transformers and switchgear, project delivery and interconnection, operation and maintenance, to end-of-life. The pack supports the manufacturing and delivery stages. It does not support raw material costs, recycling rates or decommissioning costs.

Revenue models in the pack are project-based and order-based. Gas equipment makers report backlog and slot reservations 56. Competitive auctions are expected to account for almost 60 percent of gross utility-scale renewable additions in the forecast window 3. Key stakeholders include equipment manufacturers, utilities, developers, contractors and standards bodies such as the IEEE Standards Association 12.

Source inconsistency: a 75 percent solar share of 800 GW implies about 600 GW of solar, while a separate IRENA-based summary reports a record 510 GW of solar additions 14. The gap likely reflects different definitions or scopes, but the pack does not explain it.

  • Global renewable capacity additions 800GW per year Observed Global, Latest available data [1]
  • Renewable share of installed global power capacity 49percent Observed Global, End of latest available data [4]
  • Utility-scale battery all-in capex 125USD per kWh Observed Global excluding China and United States, Latest available data [11]

3Customers, demand and adoption

Utilities, independent developers and large industrial buyers drive demand for generation and grid equipment. Demand is strong. Global renewable additions set a record 1, and construction started on over 12 GW of nuclear capacity 1. The United States installed 49 GW of renewable capacity in the latest period, a 10 percent decline from the prior year 2, so demand is not uniform across markets.

Gas turbine buyers face long waits. GE Vernova's gas power backlog and slot reservations rose from 100 GW to 116 GW in the most recent quarter, and the company expects at least 125 GW by year-end 6. Siemens Energy shipped 6 GW and booked 15 GW in its latest quarter, ending with a backlog of 69 GW 5. The pack does not provide buyer purchasing criteria. The writer's interpretation is that delivery slot certainty and price now weigh heavily, given the lead times and price increases reported 59.

Barriers include grid connection delays, financial pressures and policy shifts 2. The IEA projects competitive auctions to shape almost 60 percent of utility-scale additions 3. This is a forecast and may change with policy.

Adoption of storage is accelerating. Battery storage additions rose about 40 percent to almost 110 GW, making it the fastest growing power technology 1. The pack does not provide customer satisfaction or demand-side adoption data.

  • Gas power equipment backlog and slot reservations 116GW Observed Global, Most recent quarter [6]

4Competitive landscape and key players

Three representative provider types appear in the pack. Siemens Energy and GE Vernova supply gas power equipment and services. Hitachi Energy supplies transformers and grid equipment 568. The pack does not provide market share or concentration ratios, so market concentration cannot be measured. The writer's view is that gas turbine supply appears concentrated among a small number of large manufacturers, but this is interpretation, not a verified finding.

Business models differ. GE Vernova reports equipment backlog in US dollars, which reached $40.6 billion, up 69 percent year over year, and it expects 24 GW of annual gas turbine output in the latest year 6. Siemens Energy reports gas services backlog in GW and plans to expand transformer and gas-insulated switchgear manufacturing capacity by about 50 percent by a target year 5. Because one firm reports in GW and the other in dollars, the two backlogs cannot be compared directly.

Hitachi Energy announced a $1 billion investment in transformer and grid equipment manufacturing, including a new factory in Virginia 8. The pack does not give the investment's timing or capacity, so its effect on supply cannot be quantified.

Competitive pressure appears on price and delivery. EPRI commentary reports that gas turbine prices rose about 50 percent in six months 9. The pack holds only two primary company disclosures for gas equipment, so comparable examples are limited.

  • GE Vernova equipment backlog 40.6USD billion Observed Global, Most recent quarter [6]

5Technology, operations and workforce

The main technology categories are solar PV, wind, battery storage, gas turbines, nuclear and grid equipment. Solar and storage dominate recent additions 12. The pack includes a dataset of 1,989 utility-scale solar projects, which supports research on project-level performance but does not report performance outcomes 14.

Operational performance data is largely absent. The pack has no verified figures for productivity, yield, downtime, scrap or on-time delivery at turbine or transformer factories. Automation levels in grid equipment manufacturing are not quantified.

Interconnection requires testing. IEEE 1547.1 specifies periodic tests to confirm that interconnection functions conform to IEEE 1547 12. These requirements support operating reliability but do not report field outcomes.

Workforce is a constraint. The Bureau of Labor Statistics counts about 821,000 working electricians and projects about 72,700 openings a year. Almost 30 percent of union electricians are between 50 and 70 years old, a figure drawn from Fortune as cited by Buildforce 13. The writer's interpretation is that retirements and new openings together create a skills gap, though the pack does not quantify training pipeline output.

  • Projected electrician openings 72700openings per year Forecast United States, Latest projection window [13]

6Regulation, standards, risk and sustainability

Jurisdiction matters. This section concerns the United States unless noted. The IEEE 1547 series specifies how distributed energy resources connect with power systems and underpins many utility rules. It is a voluntary consensus standard, and it becomes binding only where a regulator, utility or contract adopts it. The pack does not identify which states or utilities have adopted it 12.

Binding rules, proposals and voluntary guidance should be kept separate. The pack contains no verified details on binding emissions limits, privacy requirements or safety statutes for this sector. Those points are not assessed here. This report is not legal or engineering advice, and readers should consult the relevant authority in their jurisdiction.

Supply risk is the most documented. Domestic production met only 20 percent of US large power transformer demand 8. Supply chain strains and grid connection delays are cited as slowing renewable additions 2. Gas turbine prices rose sharply in a short window 9.

Sustainability data is limited. The pack has no verified emissions intensity or manufacturing energy intensity figures for generation equipment. It contains no safety incident rates for the sector and no recycling or decommissioning figures. These gaps prevent a full lifecycle sustainability assessment.

  • Domestic share of US large power transformer demand 20percent Observed United States, Latest available data [8]

7Challenges, opportunities and case examples

The main constraint is equipment lead time. US average lead times are 144 weeks for generator step-up transformers, 128 weeks for power transformers and 44 weeks for medium-voltage switchgear 7. Industry analysis reports that pre-period power transformer lead times were commonly 24 to 30 months 7. The chart below compares the latest US figures.

Opportunities follow from the shortage. Domestic manufacturing investment is one response, exemplified by Hitachi Energy's $1 billion program 8. Siemens Energy plans to expand transformer and switchgear capacity by about 50 percent by a target year, a forecast 5. These plans suggest that manufacturers see sustained demand, but they do not show that capacity will close the gap.

Case example 1: Siemens Energy. The company's gas services backlog reached 69 GW, lead times now run three years or more, and it plans capacity expansion 5. Case example 2: GE Vernova. Its gas power backlog reached 116 GW, and it expects 24 GW of annual output 6. Case example 3: Hitachi Energy. Its $1 billion investment includes a new Virginia factory 8. Comparable examples are limited, since the pack includes only two primary company disclosures for gas turbines.

US average lead times for grid equipmentweeks
  • Generator step-up transformer144 weeks
  • Power transformer128 weeks
  • Medium-voltage switchgear44 weeks

Average US lead times by equipment type in the latest available data. Source definitions are not stated, and figures come from secondary industry analysis.

Source: Broadview Capital (industry analysis, citing average US lead times)

View the data
ItemValue
Generator step-up transformer144 weeks
Power transformer128 weeks
Medium-voltage switchgear44 weeks

8Outlook and strategic implications

Near term, demand for turbines, transformers and switchgear is likely to remain high, given large backlogs and lead times of three years or more 56. The writer's interpretation is that delivery schedules, rather than demand, will set project timing for much of the gas and grid build-out.

Medium term, the IEA projects almost 4,600 GW of cumulative renewable additions, a forecast 3. Storage is expected to keep growing, given its recent pace 1. The pace will depend on grid connection progress, financing and policy, which the IEA identifies as uncertain 2.

Implications for stakeholders differ. Utilities and developers should plan for long equipment lead times and price volatility 79. Manufacturers should weigh the risk of overbuilding against shortages, using the forecasts as one input. Workforce planners should note the projected openings and the aging of the electrician base 13. Standards bodies and regulators should track adoption of IEEE 1547 requirements 12.

9Conclusion

The central assessment is that demand for power generation and grid equipment is strong, but delivery capacity is the binding constraint. The most defensible takeaways are that US grid equipment lead times are long 7, gas turbine orders are backlogged for years 56, and skilled labor is tight 13. Data on manufacturing performance, safety and emissions remains unavailable in the pack.

How this was built

The report uses only the source pack. Facts are labeled by source and type. Forecasts from the IEA, EPRI commentary and company projections are identified as forecasts or interpretations. The writer's interpretive statements are marked as such. Several sources are secondary, and definitions differ across sources.

Limits to keep in mind

  • No verified figures exist in the pack for manufacturing output, capacity utilization, yield or defect rates by manufacturer.
  • No verified productivity, scrap or on-time delivery figures exist for turbine or transformer factories.
  • No verified emissions intensity or manufacturing energy intensity figures exist for generation equipment.
  • No verified project cost and schedule variance statistics exist across a consistent sample of power projects.
  • No verified safety performance indicators, such as incident rates, exist for the power equipment or construction sector.
  • Lead time figures come from secondary sources with inconsistent definitions. Only the Siemens Energy and GE Vernova disclosures are primary company reports.

Sources

  1. 1

    Global Energy Review - Key findings

    International Energy Agency Official statistics

    iea.org
  2. 2

    Global Energy Review - Technology: Solar PV and wind

    International Energy Agency Official statistics

    iea.org
  3. 3

    Renewables - Renewable electricity

    International Energy Agency Official statistics

    iea.org
  4. 4

    Renewable energy statistics and cumulative capacity

    International Renewable Energy Agency (via Earth.org report) Official statistics

    earth.org
  5. 5

    Gas Power and Siemens Energy backlog disclosures

    Utility Dive reporting on Siemens Energy earnings presentation News report

    utilitydive.com
  6. 6

    GE Vernova Q2 Form 8-K

    GE Vernova Inc. Company report

    sec.gov
  7. 7

    Power transformer and generator step-up lead times

    Broadview Capital (industry analysis, citing average US lead times) Market research

    broadviewcapital.com
  8. 8

    Solving the Gridlock: America's Electric Supply Chain Opportunity

    Rocky Mountain Institute Industry association

    rmi.org
  9. 9

    Lazard LCOE and gas turbine cost reporting via EPRI

    Electric Power Research Institute (Bobby Noble, commentary in Utility Dive) Industry association

    utilitydive.com
  10. 10

    Utility-Scale Solar Data Update

    Lawrence Berkeley National Laboratory Peer-reviewed

    emp.lbl.gov
  11. 11

    Battery storage cost: all-in BESS capex

    Ember Energy Market research

    ember-energy.org
  12. 12

    IEEE Standard 1547 for distributed energy resource interconnection

    IEEE Standards Association Standard

    standards.ieee.org
  13. 13

    Electrician and power workforce projections

    Bureau of Labor Statistics (as cited by Buildforce) Official statistics

    buildforce.com
  14. 14